CIP-002-5.1a R1—CIP-002-5.1a R1
>Control Description
Each Responsible Entity shall implement a process that considers each of the following assets for purposes of parts 1.1 through 1.3: [Violation Risk Factor: High][Time Horizon: Operations Planning]
I. Control Centers and backup Control Centers;
ii. Transmission stations and substations;
iii. Generation resources;
iv. Systems and facilities critical to system restoration, including Blackstart Resources and Cranking Paths and initial switching requirements;
v. Special Protection Systems that support the reliable operation of the Bulk Electric System; and
vi. For Distribution Providers, Protection Systems specified in Applicability section 4.2.1 above.