Under active development Content is continuously updated and improved · Last updated Feb 18, 2026, 2:55 AM UTC

CIP-014-3 R1CIP-014-3 R1

>Control Description

Each Transmission Owner shall perform an initial risk assessment and subsequent risk assessments of its Transmission stations and Transmission substations (existing and planned to be in service within 24 months) that meet the criteria specified in Applicability Section 4.1.1. The initial and subsequent risk assessments shall consist of a transmission analysis or transmission analyses designed to identify the Transmission station(s) and Transmission substation(s) that if rendered inoperable or damaged could result in instability, uncontrolled separation, or Cascading within an Interconnection. [VRF: High; Time-Horizon: Long-term Planning]

Ask AI

Configure your API key to use AI features.